WSSC contractors Spiniello and Royale are scheduled to continue work in an initiative to improve sewer and drainage systems throughout the Town. ‘No parking’ signs have been posted in various areas where work is being scheduled.
The work will span the following locations:
• 6300 Block of Jason
• 2400, 3000 & 3100 Block of Parkway
• 2800 & 3100 Block of Laurel
• 6200 & 6300 Block of Inwood
• 2800 Block of Hillside
• 6400 Block of Forest
• 2800 Block of 64th
This project is expected to take place over the following 2-week period, weather permitting. Please see the schedule regarding the upcoming work.
Thank you for your patience and understanding as this work is executed. Please see the contact information below if you have any questions or concerns.
WSSC Contact Information:
• Christopher Ball, Pipeline Construction Inspector, 202-731-6850 Christopher.ball@wsscwater.com
• Christopher Bush, WSSC Inspector, 202-489-5681, Christopher.Bush@wsscwater.com
• Emergency Call Center (301) 206-4002 or emergencycallcenter@wsscwater.com
• David Wilkins, WSSC Costumer Advocate, (301) 206-4371 or David.Wilkins@wsscwater.com
Spiniello Contact Information:
• Jeff Saldana, on-site contact, 610-496-0040
Royale Contact Information:
• Chris Gaines, on-site contact, 301-809-0908