WSSC contractor Spiniello is scheduled to continue work in an initiative to improve sewer and drainage systems throughout Town.   
 
This work will span along the 6200 Block of Forest Road 
 
 This project is expected to take place over the following 2-week period, weather permitting. Additionally, manhole rehabilitation will take place in multiple locations.
Please see the attached for more specific information regarding the upcoming work schedule
 
 
 2-week Schedule Update 9/18- 9/29
 
Thank you for your patience and understanding as this work is executed. Please see the contact information below if you have any questions or concerns.
 
 WSSC Contact Information:
 • Christopher Ball, Pipeline Construction Inspector, 202-731-6850 Christopher.ball@wsscwater.com
 • Christopher Bush, WSSC Inspector, 202-489-5681, Christopher.Bush@wsscwater.com
 • Emergency Call Center (301) 206-4002 or emergencycallcenter@wsscwater.com
 • David Wilkins, WSSC Costumer Advocate, (301) 206-4371 or David.Wilkins@wsscwater.com
 
 Spiniello Contact Information:
 • Jeff Saldana, Spiniello Superintendent/On-Site Contact, 610 496-0040