WSSC Task 201: 2-week Schedule Update 7/17- 7/28

pw
WSSC contractors, Equix and Triangle, are scheduled to continue working to improve sewer and drainage systems throughout Town.   
 
 This work will span the following locations:  
 
  • 3100 Parkway 
  • 6209 Inwood 
  • 3124 Parkway 
  • 6305 Jason 
 
This project is expected to take place over the following 2-week period, weather permitting. Additionally, manhole rehabilitation will take place in multiple locations. Please see the schedule below for more specific information regarding the upcoming work schedule
 
task
 
 
Thank you for your patience and understanding as this work is executed. If you have any questions or concerns, please reference  the schedule above for direct on-site contacts or WSSC via the contact information listed below.  
 
WSSC Contact Information:   
Equix: 
  • James Carpenter, on-site contact (443) 890-8006 
 
Triangle Contact Information: 
  • Steve Loughry, on-site contact (301) 788-2246