WSSC Task 201: 2-week Schedule Update 2/26-3/8

pw
WSSC contractors, Spiniello Co. and AMCS, are scheduled to continue work in an initiative to improve sewer and drainage systems throughout the Town.

This work will span the following location(s): 2500 Block of Wayne Place.

This project is expected to take place over the following 2-week long period, weather permitting. Please see the spreadsheet below for more specific information regarding the upcoming work schedule.
 
pw
 
Direct questions and/or concerns regarding the spreadsheet to the appropriate contact listed below.

WSSC Contact Information:

• Christopher Ball, Pipeline Construction Inspector, 202-731-6850 Christopher.ball@wsscwater.com
• Christopher Bush, WSSC Inspector, 202-489-5681, Christopher.Bush@wsscwater.com
• Emergency Call Center (301) 206-4002 or emergencycallcenter@wsscwater.com
• David Wilkins, WSSC Customer Advocate, (301) 206-4371 or David.Wilkins@wsscwater.com
 
On-Site Contact:
 
• Jeff Saldana, On-Site Superintendent, (610)496-0040